The FOTOPUR Operational Group is investigating the installation of floating solar panels on slurry lagoons to reduce ammonia emissions and generate renewable electricity without occupying additional land.
- The FOTOPUR Operational Group is investigating the installation of floating solar panels on slurry lagoons to reduce ammonia emissions and generate renewable electricity without occupying additional land.
- Two prototypes installed on farms in Zamora and Zaragoza allow us to evaluate the behavior of this technology under real conditions.
- Initial measurements show a reduction in emissions in the covered areas, while the facilities have generated around 53 MWh
The storage of pig slurry on pig farms generates ammonia emissions that affect air quality and the environment. Reducing its impact is one of the challenges facing the sector, which needs to incorporate solutions capable of improving the management of this waste and facilitating compliance with regulatory requirements.
To address this challenge, the Operational Group (OG) FOTOPUR is investigating how to combine covering manure lagoons with installing floating photovoltaic systems. The initiative aims to utilize these surfaces to produce renewable electricity and reduce emissions, without requiring additional land.
Floating photovoltaics to utilize slurry lagoons
The project studies different photovoltaic systems available on the market to identify which ones can be adapted to the conditions of the ponds. Its main lines of work are:
Technological evaluation: analysis of float models and adaptation of their structures to the characteristics of the rafts.
Emission measurement: comparison of gases emitted in covered and uncovered areas.
Energy production: study of the electricity generated and its relationship to the consumption needs of the farms.
Durability: evaluation of the resistance of materials to moisture and corrosive conditions of slurry.
The Tauste Swine Health Defense Group (ADS) No. 1 , the coordinating entity for the project, highlights the economic potential of this solution compared to other alternatives: “One of the lessons learned is that the photovoltaic cover is, currently, the only pond cover that can pay for itself.” However, it is still necessary to verify that the materials withstand the slurry environment and that the investment is worthwhile compared to other options.
Two prototypes to test their functionality
One of the main actions of GO FOTOPUR has been to install two demonstration prototypes in pig farms in Zamora and Zaragoza , with different electrical connection systems:
Granja El Chano Pork SL (Calzada de Tera, Zamora): breeding sow farm connected to the electrical grid, with a 33 kWp installation in operation since November 2025.
Puy Ovil Farm (Tauste, Zaragoza): fattening farm isolated from the grid with a 9.44 kWp system that has batteries and support from a generator set.
Between November 2025 and October 2026, the Zamora facility produced around 40 MWh, equivalent to 23% of the farm's electricity consumption . Meanwhile, the Tauste prototype generated approximately 13 MWh, covering roughly 82% of the farm's energy needs.
Initial results in emissions reduction
In addition to electricity production, the project analyzes the capacity of these systems to reduce emissions from the ponds. The Polytechnic University of Cartagena (UPCT) has carried out four measurement campaigns at both sites following the VERA protocol , a European technology verification system that allows for the evaluation of environmental effectiveness.
The results of the first campaign, conducted in April 2026, show that the covered area emitted significantly less ammonia and greenhouse gases than the uncovered area. These data are still preliminary and will need to be compared with the analysis of the remaining campaigns, which will allow for a study of emissions trends throughout the year.
Another pending aspect is to verify the resistance of the materials after more than a year of exposure to the conditions of the ponds, as well as to determine the maintenance needs of the facilities.
Participants and funding
The GO FOTOPUR is a supra-regional project, developed in Aragon and Castile and León, and coordinated by ADS nº1 Porcino de Tauste, with the participation of:
Polytechnic University of Cartagena.
The FOTOPUR coordination team emphasizes the value of collaboration between the different participating profiles: “The main value of the Operational Group is to bring together profiles from different sectors that complement each other to achieve the project's objectives.”
The initiative runs from 2024 to 2027 and has a budget of €532,313.82, funded by the Strategic Plan for the Common Agricultural Policy (PEPAC) 2023-2027 through the European Agricultural Fund for Rural Development (EAFRD) . Work will continue until April 2027, when the technical, economic, and environmental assessment of the solution is expected to be completed, and its potential application on other pig farms will be studied.